Lifting large-size UHPC curtain wall panels (panel area ≥6m²) requires a combination of specialized equipment, including vacuum suction cup lifters (suction force ≥200kg per point), balance beams (for adjusting tilt angle), and intelligent control systems (real-time load monitoring). In the 120,000m² roofing project of the Hainan International Convention and Exhibition Center, Qinglong Group used 16-point vacuum suction cups to lift 10m×3m large panels, each weighing 1.2 tons, with installation errors controlled within ±2mm. Lifting tool selection must consider panel weight, dimensions, and wind load: mechanical suction cups for weights ≤800kg, hydraulic ones for >800kg; curved panels require universal suction cups; wind-resistant ropes should be added in strong wind. Safety is the first principle of lifting, and operating procedures must be strictly followed.
The number of suction cups is calculated based on panel weight (safety factor ≥3), with suction surface flatness ≤2mm. Qinglong Group's suction cups undergo regular testing, with vacuum degree ≥-0.08MPa. In the Nanning New Media Center project, curved panels used adaptive suction cups, successfully lifting 500 irregularly shaped panels. Operators must be trained and certified, with a 100% certified operation rate.
Balance beams can adjust panel levelness, and laser positioning devices guide placement. We have developed an intelligent lifting system that displays load data in real time. Operations stop when wind speed exceeds 10m/s—safety first.
Lifting plans are verified by experts, and on-site safety supervision posts are established. A 28-year zero-accident record makes us trustworthy. Scientific lifting achieves a win-win of efficiency and safety.