What Factors Should Be Considered in the Hoisting Plan for Super-Large GRC Shapes? Qinglong GRC Large Component Hoisting Technical Specification

2026-01-04 15:05:06

Click:

Lifting of super-large GRC shaped components requires comprehensive consideration of: component weight (≤20t), lifting point arrangement (≥4 points), lifting equipment safety factor (≥6), wind speed limit (≤ level 5), and foundation bearing capacity (≥100kPa). Optimize lifting point positions through finite element analysis and control lifting stress to ≤1/5 of material strength, ensuring safe and stable lifting.

Scheme design: a large sculpture weighing 15t adopts 8-point lifting with a 200t crane, with lifting stress controlled within 6MPa. Qinglong GRC professional lifting schemes ensure safe and efficient installation of large components.

Lifting Point Design Calculation

Number of lifting points ≥4, evenly distributed. Positions determined through calculation, avoiding damage-prone areas. Safety factor ≥6, and ≥8 for critical components. Trial lifts are conducted for verification to ensure reliability.

Lifting Equipment Selection Requirements

Lifting slings must have a safety factor ≥6 and be free of damage. Hooks must have locking devices to prevent detachment. Spreader beams must have sufficient rigidity to maintain stability. Auxiliary tools must be complete for convenient operation.

Site Condition Control

Foundation bearing capacity must be sufficient, with reinforcement if necessary. Wind speed ≤ level 5; stop operations if exceeded. Space must meet slewing radius requirements. Personnel must hold valid certifications and operate according to regulations.

Emergency Plan Preparation

Response plans for sudden weather changes. Measures for handling equipment failures. Emergency plans for unexpected situations. Medical rescue preparations in place.

Large component lifting must be absolutely fail-safe. Qinglong GRC professional solutions ensure safe and smooth completion.

0
What Factors Should Be Considered in the Hoisting Plan for Super-Large GRC Shapes? Qinglong GRC Large Component Hoisting Technical Specification
Long by picture save/share
文章推荐
Image display

Home     |    Products     |    Portfolio     |    News     |    Join Us     |    About Us     |    Contact Us

 Company Address: Room 302, No. 22 Dongming Road, Shiqi District, Zhongshan City, Guangdong Province

Customer Service Hotline: 400-777-2203

Business Hotline: 0760-88706348      Mobile: 13902597531

Email : qlfsgrc@163.com

 

 Scan  WeChat

Copyright © Guangdong Qinglong Construction Engineering Co., Ltd. All Rights Reserved  . Recordation Number: 粤ICP备13069248号-24

Service Center

Please choose online customer service to communicate

Contacts
Contact number
13902597531
Scan a QR Code
Qrcode
Scan with WeChat
  • Cancel
Add WeChat friend to learn more about the product
Use Enterprise WeChat
"Scan" to join the group chat
Copy success!
Add WeChat friend to learn more about the product
I see.