GRC installation must follow a standardized process, generally divided into six stages: preparation, measurement and layout, substrate treatment, panel installation, joint treatment, and cleaning and acceptance. Each stage has strict technical requirements.
In the Shanghai Century Plaza renovation project, the Qinglong installation team strictly followed the standardized process: first, an on-site survey was conducted, using a 3D scanner to obtain substrate data; then BIM models were used for installation simulation to optimize the installation sequence; installation proceeded from bottom to top, center first then sides, completing a fixed area each day; joint treatment used specialized sealant applied in two passes; finally, comprehensive inspection and acceptance were carried out. This standardized operation ensured the project was completed with high quality.
Verify drawings against on-site dimensions; adjust if errors exceed tolerance. Check panel numbering, quantity, and quality; replace damaged panels. Prepare construction tools and check safety devices. Conduct technical briefings to clarify key points.
Set installation datum lines with accuracy of ±1mm. Snap panel grid lines clearly and accurately. Recheck substrate dimensions and record deviation data. Layout lines must be verified and confirmed after completion.
Substrate strength must meet standards, free of hollowing and cracking. Flatness deviation ≤4mm/2m. Waterproofing layer intact, free of leaks. Embedded parts accurately positioned, firm and reliable.
Install panels in numbered sequence to prevent mix-ups. Fix hangers securely and adjust into position. Keep panel joints even and consistent in width. Inspect and correct promptly to ensure quality.
Strict adherence to the standard process guarantees installation quality. Qinglong GRC's standardized installation system ensures every project is presented perfectly.