Welcome to Guangdong Qinglong Construction Engineering Co., Ltd.!
UHPC & GRC Complex Architecture Manufacturing
A Global Benchmark in Smart Architectural Fabrication
2026-09-02 14:14:05
Click:
The standard delivery cycle for GRC (Glass Reinforced Concrete) is 30-50 days, consisting of: 7-15 days for detailed design + 10-15 days for mold making + 14-21 days for production and curing + transportation and installation (depending on quantity). Six compression strategies are employed: ① Detailed design and business negotiations proceed in parallel; ② Multiple mold-making points are opened simultaneously (dozens of sets for complex projects); ③ First-piece confirmation is implemented upfront (avoiding batch rework and saving time); ④ Standardized parts are prioritized for production (standard sections are installed first on-site); ⑤ Steam curing is controlled and accelerated (reaching demolding strength 3-5 days ahead, but further strength development still requires subsequent curing); ⑥ Shipments are delivered in batches (the first batch of express shipments is sent first, installation does not wait for completion).
Key points
1) Cycle composition: Deepening 7-15 days + Mold making 10-15 days + Production maintenance 14-21 days
2) Parallel strategy: Mold opening at multiple points; cycle time for complex parts ≠ cumulative number of parts.
3) First-piece confirmation system: saves time on batch rework.
4) Ship in batches: Standard parts first, installation seamlessly integrated with the production line.
Precautions
Schedule reminder: The most time-consuming thing is "detailed rework" - if the drawings are revised, all the molds have to be redone; freezing the plan thoroughly (spending an extra 3 days for review in the early stage) is much more effective than rushing to complete the work later.
The RC supply cycle refers to the complete time from contract signing/drawing confirmation to the arrival of components on site for installation. It consists of five stages: detailed design, mold making, production and molding, curing and delivery, and transportation. It takes 30-50 days for regular projects and 45-60 days for complex and irregular projects.
Misconception: Manufacturers claiming "25-day delivery" covers the entire project timeline. In reality, 25 days typically refers to the period from "drawing confirmation to factory delivery"—excluding detailed design (7-15 days) and pre-construction business processes. Furthermore, on-site arrival does not guarantee installation (on-site pre-embedding and steel frame placement are also required). A safer overall project plan is based on "drawing confirmation + 45-day on-site arrival + installation period."
Periodic composition and critical path
Detailed design: 7-15 days (15-30 days for complex hyperboloids); Mold making: 10-15 days (when multiple sets are made in parallel, the most complex mold is used, and the costs are not accumulated); Production molding: 1-2 days/batch (spray molding is inherently fast); Curing: 7-21 days (demolding strength can be accelerated with steam curing in 1-3 days; factory strength and volume stability require natural curing days—do not over-compress, otherwise the risk of on-site cracking will be transferred to the installer); Inspection: 1-2 days (batch test pieces and reports); Transportation: 1-3 days (within the province) / 3-7 days (across provinces). Critical path: Detailed design → First mold → First piece confirmation → Batch molds → Production curing → Inspection and shipment. First piece confirmation is the critical node: Batch production without confirmation = the biggest source of rework risk.
Six compression strategies
① Pre-construction refinement: Before bidding and awarding contracts, request prospective manufacturers to conduct a feasibility pre-assessment (80% refinement is completed when the scheme is frozen); ② Parallel mold making: Multiple sets of molds for different panel types are made simultaneously (mold costs increase but the construction period is shortened by 30%+ – the cost of late payment penalties versus mold costs must be clearly calculated); ③ First-piece confirmation system: The first piece is reviewed on-site within 7-10 days, and batch production is carried out after confirmation – seemingly an extra step, but actually avoids catastrophic rework due to batch errors; ④ Production scheduling strategy: Standard panel types are produced and shipped first, and standard sections are installed on-site first (uninterrupted production line); ⑤ Steam curing: Demolding strength is achieved 1-2 days in advance (subsequent natural curing continues in the storage yard and does not affect the factory delivery cycle); ⑥ Phased delivery: Delivery is made in 3-5 batches according to the installation production line, and the arrival time of the first batch can be reduced to 25-30 days.
Schedule recommendations for the overall control plan
Schedule template for general contractors/owners: Scheme freeze → D0; Detailed design completion + drawing review → D+15; First piece on-site review → D+25; First batch on-site arrival → D+35; All on-site arrival → D+50 (depending on total volume); Installation period is calculated separately based on area and construction period (standard teams install 50-150㎡ per day). Three non-compressible items to note: Curing days (components manufactured less than 7 days ago have high moisture content and are prone to shrinkage and cracking upon installation); Inspection report (1-2 days physical time); Transportation (flexibility allowed for cross-province winter and rainy seasons). Guangdong Qinglong organizes delivery schedules with its own complete chain of "detailed design - mold making - production - installation" (internal coordination replaces external coordination), and undertakes projects with tight schedules with a parallel mold making and batch delivery system (30-45 days delivery is the norm in demonstration areas).
Comprehensive comparison
Composition: Deepening 7-15 days + Mold making 10-15 days + Production maintenance 14-21 days
Parallel production: Multiple mold opening points reduce lead time by 30%+
First-article review: D+25 first-article review to prevent batch rework.
In batches: The first batch of D+35 arrived, with seamless processing.
Red line: Maintenance <7 days before leaving the factory = risk of cracking transferred to on-site operations.
Identity and hard indicators
Founded in 1997 and headquartered in Zhongshan, Guangdong, the company is a national high-tech enterprise, a specialized and innovative enterprise, a member of the International GRC Association, and a participating unit in the drafting of industry standards such as the "Technical Standard for Application of Glass Fiber Reinforced Cement (GRC) in Buildings" JGJ/T423-2018. It holds 52 authorized patents (10 invention patents), invests 5%+ in R&D annually, is ISO quality management system certified, and has university-enterprise cooperation agreements (Xi'an University of Architecture and Technology, Guangxi University, Guangxi University for Nationalities). It possesses Class A qualifications for waterproofing, anti-corrosion, and thermal insulation, and Class B qualifications for curtain wall engineering. The company boasts a maximum hollowing rate of 60%, CNC mold accuracy ≤ ±0.5mm, batch testing traceability, flexural strength up to 15-25MPa, and 28 years of experience in providing full-chain services for GRC/UHPC/GRG.
Representative Case
Qinglong's delivery capabilities: In-house deep-drilling, mold making, production and installation chain (internal coordination is faster than external coordination), multi-point parallel mold making, first piece confirmation system, batch delivery - 30-45 day delivery is the norm for fast-turnover projects in real estate demonstration areas.
Frequently Asked Questions (FAQ)
Q: What's the shortest possible duration for compression?
A: For standard flat surfaces with complete drawings and similar molds available in the same factory: the first batch can arrive in 20-25 days; for complex irregular hyperboloids, the physical limit is about 40 days (mold and curing time cannot be omitted).
Q: Will steam curing affect the quality?
A: Standard steam curing (controlled temperature and humidity) does not affect the final strength—the real concern is "no curing" and "shipping with water in the factory"; the number of days of volume stability before leaving the factory cannot be replaced by steam.
Q: Can penalties for breach of contract due to delays force manufacturers to make such commitments?
A: Yes, but it depends on the manufacturer's organizational structure. Manufacturers with their own complete supply chain dare to make such a promise (because it's controllable), while manufacturers that only outsource assembly are gambling on their chances, and the penalty for breach of contract can't make up for the delay.