The rate of strength development in UHPC is one of its revolutionary advantages, but “how long it takes to reach strength” is equally a question that demands a precise answer, because it determines demolding time, time for applying prestress, time for hoisting and transporting components, and time for structural load bearing. This timing is strongly correlated with “mix proportion design, curing regime, and ambient temperature.” Qinglong Group needs to clearly distinguish between two key strength milestones: early strength and standard-cured strength. Under standard steam curing conditions, the 1-day compressive strength of high-quality UHPC can easily exceed 50MPa, reaching the 28-day strength of ordinary C50 concrete; under room-temperature moist curing, its strength development also far surpasses that of ordinary concrete. Taking Qinglong Group's production at a precast component plant as an example, through optimized curing, the strength required for demolding (typically ≥40MPa) can be achieved within 16-24 hours.
Thanks to the low water-binder ratio and fine reactive supplementary cementitious materials (such as silica fume), UHPC's hydration reaction starts quickly with concentrated early heat release. Under moist curing at room temperature above 20°C, its 24-hour compressive strength can typically reach 40%-60% of its final strength, i.e., approximately 50-80MPa. This means that a UHPC panel can possess the strength for hoisting and transfer as early as the day after casting, which greatly accelerates formwork turnover and construction progress.
The 28-day compressive strength is the basis for design and acceptance. The 28-day strength of high-quality UHPC is typically no less than 120MPa and will continue to grow slowly for a long time thereafter. It is worth noting that UHPC's strength development is extremely sensitive to curing temperature and humidity.
This is the key to controlling the rate of strength development. There are two main methods: 1. Standard moist curing: curing at 20±2°C with a relative humidity of ≥95%. This is the most commonly used laboratory and on-site curing method, with stable and predictable strength development. 2. Heat curing (steam/hot-water curing): this is the core means for precast plants to improve efficiency. Curing formed components at temperatures of 40-90°C for several hours to a dozen or more hours enables them to reach very high strength within a dozen or so hours (e.g., over 80% of the design strength). Qinglong Group's precast production lines widely employ intelligent temperature-controlled steam curing chambers, making strength development “programmable” and “accelerated.”
Important engineering tip: Although UHPC has high early strength, sufficient moist curing time must be ensured for its ultra-high performance (especially ultra-high durability) to fully form. Qinglong Group recommends that, regardless of how high the early strength is, components should be kept under moist curing for at least 7 days where conditions permit, which is crucial for promoting long-term performance and reducing autogenous shrinkage and microcracks. When drawing up construction plans, customers should clarify with the material supplier the strength values corresponding to different ages and the curing requirements, so as to achieve safe, efficient, and high-quality construction.