The delivery time of GRC products is affected by factors such as product complexity, order quantity, and production processes, typically ranging from 15-45 days. Standard panels (flat panels, single-curved panels) have a production cycle of 15-20 days, shaped components 20-30 days, and complex double-curved panels and large components 30-45 days. Through lean production management and intelligent scheduling systems, Qinglong GRC achieves an on-time delivery rate of up to 98%, and urgent orders can be shortened to 10-15 days.
Cycle control measures: establishing a standard lead-time database for accurate production time estimation; using an ERP system to optimize production planning; running key processes in parallel to reduce waiting time; monitoring progress in real time and adjusting resources promptly. For one key project with a tight schedule, Qinglong GRC optimized production scheduling and delivered 5 days ahead of schedule, ensuring smooth project progress.
For standard products such as flat panels and single-curved panels, mold preparation takes 3-5 days, production 10-12 days, and curing 2-3 days, totaling 15-20 days; batch orders can use flow-line production to further shorten the cycle. Standardization improves efficiency.
Shaped components require custom molds: mold making takes 5-7 days, production 12-15 days, and curing 3-5 days, totaling 20-30 days; complex components require multiple trial productions, appropriately extending the cycle. Allow sufficient time for custom products.
For double-curved panels, large components, and similar products, mold making takes 7-10 days, production 15-20 days, and curing 5-7 days, totaling 30-45 days; segmented fabrication and on-site assembly can shorten the factory cycle. Large projects require meticulous planning.
Urgent orders can be shortened to 10-15 days through optimized scheduling, parallel operations, and adjusted curing regimes; an expedited fee applies, and other orders may be affected. Rush services meet urgent needs.
Accurate delivery times safeguard project schedules. With scientific management, Qinglong GRC ensures on-time delivery.