The delivery lead time for custom UHPC panels is determined comprehensively based on panel complexity, order quantity, and process requirements, typically 25-45 days. Standard flat panel products (thickness ≤30mm, flat panels) take 25-30 days; shaped panels (single-curved surfaces, shallow relief) require 35-40 days; complex double-curved panels or large components require 40-45 days. Through standardized process management and a flexible production system, Qinglong UHPC maintains an on-time delivery rate above 98.5%.
The production cycle breaks down in detail as follows: technical coordination and detailed design, 5-7 days; mold fabrication, 7-10 days; production casting and curing, 10-12 days; surface treatment and inspection, 5-7 days; logistics and transportation, 3-5 days. In a key project, Qinglong UHPC compressed the conventional 40-day delivery period to 30 days through parallel operations (design and mold making conducted simultaneously) and an optimized curing regime, ensuring critical project milestones.
Panel complexity: flat panels 25-30 days, single-curved panels 30-35 days, double-curved panels 35-45 days; order quantity: small-batch orders under 100㎡ increase the production cycle by 15%; these factors require advance planning.
Modular mold design reduces mold fabrication time by 30%; optimizing the steam curing regime shortens curing time from 72 hours to 48 hours; these measures effectively improve efficiency.
Rush orders under 100㎡ can be compressed to 20 days with a 30% rush fee; these solutions address urgent needs.
An alternative supplier database ensures raw material supply; a 10% capacity buffer is reserved for unexpected situations; these measures safeguard delivery.
Delivery lead times require scientific management. Qinglong UHPC plans precisely to ensure on-time delivery.